West Mulia Coal Port Project

Kontraktor Dermaga - West Mulia Coal Port Project

PT. Dharma Subur Satya (DSS) just completed the EPC Project of West Mulia Coal Port Project with our client PT. Mitratama Perkasa (PT. Arutmin Group) at Kintap, South Kalimantan. The scope of works consist of Engineering, Procurement & Construction for 2 x 8000 DWT jetty capacity, Loading Conveyor System of 2000 Ton per hour, Stacker Conveyor, Civil Works, MCC Control Room, Steel Structure and Mechanical & Electrical. DSS completed all scope of works on schedule within 18 months accordance with Owner target . And DSS also has achieved 516 working day and 753,725 Manhours without Accident and Loss Time Injuries.

Both comments and pings are currently closed.
This theme is sponsored by things to do in new york along with musical logos, Music and EMR softwares